Fesco New Connection/Online demand notice application
Are you looking for a Fesco new connection? and you are worried about how it will happen, So you don’t need to worry about it. In this article, we deeply discussed how to apply for it.
Now fesco provides an online portal for applying for a new electricity connection, So you don’t need to contact any helpline or visit government offices, You can easily do it from your home. You can also check you fesco bill from here
Fesco New Connection Eligibility Criteria?
Eligibility criteria rely on which connection you are installing. There are two types of connection one is a Commercial connection and the other one is a Residential connection, Your information like your name, address, contact information will be required for the application.
Residential Connection Requirements
- Valid NIC (National Identity Card).
- Proof of ownership of the property.
Commercial Connection Requirements
- Valid NTN (National Tax Number).
- Lease agreement.
- Business registration documents.
After filling all the necessary documents you will need to attach:
How to Apply for FESCO New Connection
Two ways to apply Fesco’s new connection. Online and Offline.
Online Application Process
- The very first thing you need to visit (ENC’s official online portal.
- Then click on the Apply button on the right side of the portal.
- Enter your distributing company name Llike (Fesco) And your Neighbor reference number in the box.
- Once you enter this data, Now you have to select the connection type ( Residencial or Commerical) check the Domestic if you need residential, and select corresponding if you need a Commerical connection.
- After this Fill out the personal details given below.
- Select the landlord option where you need a new connection, If any chance if don’t have property select the ‘tenant’ option
- Enter your name your father’s name and your husband’s name.
- Select your city, If you are from Pakistan simply select Pakistan, and if you are out of Pakistan select foreigner.
- Enter your CNIC or NIC in the box.
- In the mobile number section first enter your Active phone number and in the other one enter your father or husband’s number.
- Enter your personal detail information in the box given below.
- And also fill out the premises detail.
- After providing all the information you will ask for the attached scanned copies, So you have to attach these because these are the necessary information. Remember one thing before providing these scanned copies make sure you are providing the correct information.
- After providing this information select the submit button, it will ask you to solve the captcha and accept the terms and conditions, now you are done with your job.
Offline application process
Follow the steps given below
- Visit the sub-decision of Fesco near to you.
- Get an online application form free of cost.
- fill out it with the information given on the form, Attach your documents.
- Now submit the application in the customer center.
- After you submit the form, Fesco will give you the estimated cost for the connection.
- Now you are done Fesco will provide you new connection at a specific time.
FESCO Demand Notice for New Connection
After submit the new meter application, Fesco will verify your request. When your application will verify. Fesco issued a demand notice. You can download the demand notice from the ENC website Link of the website given on the above. And if you want Correction your bill reach out through our Bill correction article at our website.
Demand notice fee will mentioned on the print when you download it.Fesco online demand notice fee depend on the connection you are installing. Usually fee for new connection is 9000 + 800 cost for the guarantee for the 3KW.
Connection Type | Length of Service Line | Fee (PKR) |
Single Phase (Rural) | Up to 40 meters | 4000 |
Single Phase (Urban) | Up to 40 meters | 4000 |
Three Phase | Up to 40 meters | 15000 |
Submit your Demand notice fee within the date otherwise your notice can expire. Usually, fesco gives 7 to 11 days to submit the fee.
you can submit your fee through the Bank of Punjab and other banks, or you can pay it through online payment methods. Once you submit your fee now you can submit your paid receipt in the Fesco office.
FESCO New Connection Tracking and Status
New Meter Connection Status
Status for the new connection meter, You can simply check your status by just entering your reference number at fesco official website. It will give you a real time updates about your application.
FESCO Demand Notice Tracking
After submitting the process for your application, As shown in the above heading fesco will issue a demand notice and you will pay a fee for the demand notice, After this process you can track your demand notice by entering the reference number that you give on the application.
FESCO New Connection Fees and Categories
For Single-Phase Connection
Description | New Connection Charges |
Length of Service Line upto 40 meters. | Rs. 9000/- |
Length of Service Line from above 40 to 100 meters (one span LT with Ant-Conductor and One Pole). | Rs. 9000+800/meter above 40 meters Length of Service Line. |
Length of Service Line from above 100 to 160 meters (2 spans LT with Ant-Conductor and two Poles) | Rs. 57,000+1000/meter above 100 meters Length of Service Line. |
For Three- Phase Connection
Description | New Connection Charges |
Length of Service Line upto 40 meters. | Rs. 35,000/ |
Length of Service Line from above 40 to 100 meters (one span LT with Ant-Conductor and One Pole). | Rs. 35,000+1000 per meter above 40 meters Length of Service Line. |
Length of Service Line from above 100 to 160 meters (2 spans LT with Ant-Conductor and two Poles) | Rs. 95,000+1100 per meter above 100 meters Length of Service Line. |
Length of Service Line from above 160 to 280 meters. | Rs. 161,000+1200 per meter above 160 meters Length of Service Line. |
Expected Time-Frame for a New FESCO Connection
Category 1: Load Up to 15 kW (400 V)
Procedure | Concerned Staff | Time-frame/Days |
Application Submission to the concerned Sub-division | SDC, LS, SDOHead Draft man/XEN/DMO | 4 |
Issuance of Demand Notice after documentsโ verification | LS, SDO/AMOHead Draft man/XEN/DMO | 6 |
Approval of Store Requisition by SCO | LS, SDO/AMOXEN/DMO | 11 |
Meter Installation | LSSDO/AMOXEN/DMO | 9 |
Total Required Days | 30 |
Category 2: Load 15-70 kW (400 V)
Procedure | Concerned Staff | Time-frame/Days |
Application Submission to the concerned Sub-division | Head Draft man/XEN/DMO | 5 |
Issuance of Demand Notice after documentsโ verification | XEN/DMO | 8 |
Approval of Store Requisition by SCO | XEN/DMO | 25 |
Meter Installation | SDO/AMOXEN/DMOXEN/DM (M& T) | 15 |
Total Required Days | 53 |
Category 3: Load 70-500 kW (400 V)
Procedure | Concerned Staff | Time-frame/Days |
Application Submission to the concerned Sub-division | Head Draft man/SE/Manager (O) | 6 |
Issuance of Demand Notice after documentsโ verification | SE/Manager (O) | 10 |
Approval of Store Requisition by SCO | PD (Construction)XEN/DMO | 20 |
Meter Installation | SDO/AMOXEN/DM (M& T)XEN/DMOXEN/DM (M& T) | 37 |
Total Required Days | 73 |
Category 4: Load Above 500 kW (11 KV or 33 KV)
Procedure | Concerned Staff | Time-frame/Days |
Application Submission to the concerned Sub-division | Manager (P& E) | 10 |
Issuance of Demand Notice after documentsโ verification | Manager (P& E) | 20 |
Approval of Store Requisition by SCO | PD (Construction)XEN/DMO | 55 |
Meter Installation | SE Manager (O)Manager (M& T)XEN/DMOXEN/DM (M& T) | 21 |
Total Required Days | 106 |
Category 5: Load Above 5000 kW (66 KV)
Procedure | Concerned Staff | Time-frame/Days |
Application Submission to the concerned CEO | Manager (P& E) | 30 |
Issuance of Demand Notice after documentsโ verification | CE (T & G)CEO OfficeMD, NTDC | 15 |
Approval of Store Requisition by SCO | CEOCE (T&G)PD (GSC) | 411 |
Meter Installation | Manager (P & E)Manager (M & T)SE/Manager (O)XEN/DM | 40 |
Total Required Days | 496 |
Conclusion
In this article we discussed Fesco’s new connection and demand notice, We try our best to cover all the information about Fesco new connection and demand notice to help Fesco consumers.